What we are doing and why

TTC will be rebuilding an existing underground utility chamber on the north side of Dupont Street in the vicinity of Kendal Avenue. The chamber is part of a network in the city that provide access to electrical and communication cabling for TTC, as well as for other utility companies.

Work

Activities will include minor roadway excavation to expose the utility chamber, rebuilding the concrete chamber and restoring the roadway. Equipment, materials and the work zone/traffic controls will remain onsite until the project is completed.

Work Zone

Beginning as early as Monday, January 11 at 7 a.m., crews will begin setting up a safe work zone and temporary traffic controls.

Traffic, parking, pedestrian and cyclist details

  • To maintain traffic movement on Dupont Street through the work zone, on-street parking will be temporarily restricted in the immediate area to allow for one lane of traffic in each direction.
  • All sidewalks, private driveways and store entrances will be maintained.
  • The work zone and traffic control will remain in place until project completion.

Work hours and timeline

Work will take place Monday to Friday between 7 a.m. and 10 p.m. Efforts will be made to complete the work sooner by working Saturdays between 9 a.m. and 5 p.m., as required.

Thank you for your patience during this essential work.

For further information:

Paul Tran, Community Liaison, 647-461-5133; paul.tran@ttc.ca.