Beginning the week of January 7, 2019 crews will be relocating some natural gas lines to make way for the future subway Line 2 East Extension. The work area will be located on Danforth Road from Eglinton Avenue East to north of No Frills Lane.

Upcoming works

  • Enbridge Gas Distribution (Enbridge) will be relocating some natural gas lines around the intersection of Danforth Road and Eglinton Avenue East.

Timing

  • Work at this location is expected to begin the week of January 7, 2019 and be completed by February 28, 2019.
  • Some work may be rescheduled due to weather conditions or unforeseen circumstances.
  • Work will take place between 7 a.m. to 7 p.m., Monday to Friday.

What to expect

  • Short term lane closures may be required in order to facilitate the work.
  • Driveways will remain open to businesses and residents.
  • Pedestrian walkways will remain open. Please watch for additional signs directing pedestrians, as detours may be required.

Traffic and Transit impacts

  • Traffic delays may be expected during construction.
  • No impacts to TTC bus stops are anticipated.
  • As always, please take care when travelling near work sites.

Gas relocation work area

Thank you for your patience as we work to improve transit in Toronto.

For further information:

Christina Joseph, Community Liaison Officer, 416-590-6753, sse@ttc.ca.

Project Information: scarboroughsubwayextension.ca

For more information about this gas line relocation work, please contact Enbridge at 416-495-4809 or enbridgegasmedia@enbridge.com.