TTC track renewal through the summer of 2018 on Broadview Avenue will require changes to the 505 DUNDAS route. Trackwork on Broadview Avenue at the intersections and between Gerrard Street and Dundas Street will renew this critical infrastructure.

505 DUNDAS buses will divert in two stages between June 24 and late August:

  • Stage 1 (Dundas and Broadview): 505 DUNDAS buses will divert in both directions from Dundas Street via River Street and Gerrard Street East to Broadview Avenue.
  • Stage 2 (Gerrard and Broadview), starting late July: 505 DUNDAS buses will divert in both directions from Dundas Street via River Street, Gerrard Street, St. Mathews Road, and Jack Layton Way to Broadview Avenue.