Construction Notices for May 2015
-
UPDATE: Landscaping of Cross Passage Area In Vanier/Founders Green, May 20 to May 31, 2015
May 21, 2015Final landscaping of the land used for a cross passage for the northern subway tunnels will begin Wednesday, May 20 until May 31, 2015.
-
Early Morning at York University Concrete Pour Scheduled for May 23, 2015
May 21, 2015A large concrete pour for the concourse level of the station box is scheduled for Saturday, May 23, 2015 at the future York University Station. The pour will begin at 6:00 a.m. and will continue until 5:00 p.m.
-
Landscaping of Cross Passage Area In Vanier/Founders Green, May 20 to May 31, 2015
May 15, 2015Final landscaping of the land used for a cross passage for the northern subway tunnels will begin Wednesday, May 20 until May 31, 2015.
-
DEFERRED UNTIL MAY 12, 2015: Lane Restrictions on Finch Avenue West East and Westbound between Tangiers Road and Romfield Lane May 8, 2015 - June 26, 2015
May 7, 2015On Friday, May 8, 2015 (for a 7 week period) Finch Avenue W. will be reduced to one lane in each direction between Tangiers Rd. and Romfield Lane.
-
Early Morning at York University Concrete Pour Scheduled for May 7, 2015
May 5, 2015A large concrete pour for the concourse level of the station box is scheduled for Thursday, May 7, 2015 from 6:00 a.m. until 4:00 p.m.