Testing and Commissioning a Subway Extension

March 24, 2017

Download a PDF version of the newsletter

TTC and contractor employees are busy testing many station systems on the TYSSE.

Photo of workers testing equipment.

The Toronto-York Spadina Subway Extension (TYSSE) is scheduled to open in December 2017, with construction work finishing at different stations throughout the year.

As construction of TYSSE nears completion, the test and commissioning phase of work to ready the subway stations for revenue service has begun. Testing and commissioning is a critical and important milestone for a subway extension project.  This process is the beginning stage for the project turning over from the construction contractors to the owner and operator, TTC.

Six new subway stations and connecting tunnels, which form the TYSSE, will extend the TTC’s existing Line 1 Yonge-University north into the City of Vaughan in York Region.

TTC employees adjusting one of the track switch machines.

Photo of workers testing equipment on subway track.

What is Commissioning?

Commissioning involves a series of tests – a full audit trail – of all equipment and systems in the subway extension, including stations and tunnels. Everything that has been placed for use in the new stations and tunnels comes with documents that explain how the item was designed and tested, as well as how the TTC should operate and maintain it. Once completed, commissioning will result in the infrastructure having been fully tested and signed off as being “Fit for Purpose”.

Testing starts at the individual component level in each station (e.g. electric heaters, air handling units and humidifiers), and progresses to larger systems such as HVAC, Power and Fire Alarm.

Once the station systems are fully tested they are linked to integrated systems, to test across station boundaries, either station to station, or station to various control centres. Integration testing involves making sure that links between systems operate as intended, and do not have any unforeseen effects. Integration testing must be completed before proceeding to full system commissioning, which involves testing the complete system functionality of the extension to the Transit Control Centre, including test train running.

The results of the tests performed under commissioning will provide evidence to allow sign off for various parts of the project's safety certification.

“This isn’t just any subway extension. This will be a Wi-Fi-, PRESTO-, Automatic-Train-Controlled subway extension,” said CEO Andy Byford. “It really will be state of the art from day one.”

With overall construction more than 92 per cent complete, the project is focusing in 2017 on testing and trial operations of the facility management, communication and railway electrical and control systems. The next key milestone will be the electrification of the traction power rail by the end of March.

First clearance train testing was complete in March.

Photo of clearance train.

 Commissioning Achievements to Date

Commissioning Next Steps

The TYSSE project is an 8.6-kilometre extension of the Toronto Transit Commission’s Yonge-University subway line from its present terminus at Downsview Station (to be renamed Sheppard West Station when the extension is complete) to the Vaughan Metropolitan Centre Station at Highway 7. It will have six new stations. The expansion of the subway will bring the line into The Regional Municipality of York. The new line is scheduled to open by the end of 2017.

For more information:
Web: spadina.ttc.ca
Call: 1-800-223-6192
Email: tysse@ttc.ca to receive regular construction notices
YouTube: Visit the Official TTC YouTube Channel
http://www.youtube.com/officialttcchannel to view our project videos.

The Toronto-York Spadina Subway Extension project is jointly funded by the Government of Canada, the Province of Ontario, the City of Toronto and The Regional Municipality of York.

Download a PDF version of the newsletter

Bus Route Changes

TTC Bus

Review the new changes to bus routes in the area to connect to the new subway extension.

Read about it here!

Need Information

To contact us for information about the project:

Call the information line: 1.800.223.6192 (live operator available 24/7)

Contact the Project

Photo Gallery

Check out the latest construction photos and project YouTube videos.

Click here to view the Photo Gallery.

Project News