Construction Schedule
View the Schedule for Advance and Major Contracts
Location |
Scheduled |
Status of |
---|---|---|
Wilson Downsview Connection | February 2010 | Complete |
Advanced TBM Launch Shaft at Steeles W | April 2010 | Complete |
Advanced TBM Launch Shaft at Sheppard W | May 2010 | Complete |
Highway 407 - Enabling Works | July 2010 | Complete |
Finch West Station - Fire Station #141 | July 2010 | Complete |
Finch West Station - Road Work & Utilities | August 2010 | Complete |
York University Detours Phase 1 | September 2010 | Complete |
York University Detours Phase 2 | November 2010 | Complete |
Major Contracts
Location |
Scheduled |
Status of |
---|---|---|
Downsview Park Station | December 2010 | Active |
Finch West Station | June 2011 | Active |
York University Station | Summer 2012 | Active |
Pioneer Village Station | September 2011 | Active |
Highway 407 Station | January 2011 | Active |
Vaughan Metropolitan Centre Station | June 2011 | Active |
Tunnelling by TBM | June 2011 | November 8, 2013 |
SEM Tunnelling | Spring 2012 | November 6, 2014 |
Track Installation | Summer 2013 | March 31, 2016 |
Scheduled start dates are tentative and subject to change due to weather and/or unforeseen events.
Advance Contracts prepare construction sites by constructing and relocating utilities and building temporary roads and detours to ready construction sites for Major Contract work.
Track, Signal, Fare Collection Systems, Communications and Integrated Controls Works continue until 2017.
Opening of the extension is anticipated for the end of 2017.