This page includes information about construction projects which impact customer travel directly. For information about major construction projects, please visit projects.ttc.ca.

Learn about when and why TTC needs to complete overnight construction to keep transit moving.

Learn about the causes of subway noise and vibration and TTC’s work to address it.

Bus stop improvements

Bus stop construction will take up to a week, pending location, site and weather conditions.

Chester Station - station improvements

Scheduled for completion in 2021

Davisville Station - bus roadway and pedestrian bridge rehabilitation

May 29, 2019 to February 2020

Don Mills Station - bus transfer level ventilation upgrades

April 2017 to early 2019

Donlands Station - second exit/entrance and Easier Access project update

Preliminary investigative work ongoing

Dufferin Street and Lawrence Avenue West - intersection improvements

August 1 to September 30, 2019

Dundas West Station - roof rehabilitation

Starting as early as March 27, 2019

Dupont Station Easier Access Project

Lane reductions at Spadina Road and Dupont Street until the end of the project

Eglinton Station - roof repair

June 3 to December 2019

Glenayr Substation - roof rehabilitation

April 29 to end of August

Glencairn Station - skylight replacement

August 2017 to December 2019

Greenwood Station Easier Access project land surveying

Ongoing

Islington Station - bus roadway concrete slab repairs

To be rescheduled

Jane Station - bus roadway, platform and station improvements

May 8 to November 2019

Keele Station - Easier Access project

As early as August 1, 2019

Kennedy Station - Eglinton Crosstown construction

May 1, 2017 until approximately 2021

Kipling Station - Metrolinx construction impacts

Reduced parking and access changes at Kipling Station

Kipling Station - bus roadway concrete sampling

To be rescheduled

Lansdowne Station - Easier Access Project 

Elevator construction in Green P Car Park 81 begins June 2019 until end of 2021

Lawrence East Station - Metrolinx work requiring pedestrian tunnel closure

July 8 to August 11, 2019

Lawrence East Station - roof rehabilitation

Mid-April 2019 to Mid-January 2020

Line 1 Yonge Subway Extension - preliminary studies

Starting as early as March 4, 2019

McNicoll Bus Garage - weekend work

Starting September 30, 2017 and onwards - 9 a.m. to 5 p.m.

Old Mill Station - electrical upgrades requiring generator use

July 19 to 21, 2019

Overhead infrastructure upgrades across streetcar network

Ongoing through spring and summer 2019

Queen Street East - essential concrete repairs

From June 25 to 28, July 2 to 4, July 8 to 12, July 15 to 19

Queen Street West at Abell Street - rail replacement

July 19 to 22, 2019

Roncesvalles Yard - modifications to track and carhouse

April 2, 2018 to Spring 2020

Runnymede Station - Easier Access (Elevator) Project

Construction from late 2018 to late 2020

Russell Carhouse - new sand silo and parking lot access

August 2019 to end of 2020

Spadina Road and Lowther Avenue - field testing

Continuing as early as February 4, 2019

St Clair Avenue Bus Underpass Bridge Rehabilitation

Warden Station PPUDO/taxi entrance and traffic impacts

Victoria Park to Warden stations - lighting upgrades

Ongoing overnight work required for safety

Wellesley Station - Easier Access project

Bus loop re-opened as of June 24, 2019; elevator work continues inside the station

Wilson Station - elevator construction

Starting as early as November 7, 2018

Wilson Station - temporary closure of Tippet Road commuter lot

Additional commuter parking available at Spadina Subway Extension stations and Yorkdale Station