Construction Notices for July 2014
-
Update - Local Closures of Keele Street Through Summer
July 22, 2014Keele Street southbound, for a 100 m section south of Finch Avenue West, is currently closed and scheduled to reopen on August 22, 2014.
-
Overnight Work at York University, Concrete Pours Scheduled for Wednesday, July 23 and July 30, 2014
July 17, 2014Overnight construction will take place on Wednesday, July 23 and July 30, 2014 from 2:30 a.m. to 3:00 p.m.
-
W.R. Allen Road Lane Restrictions North of Sheppard Avenue West, July 18 – July 21, 2014
July 17, 2014W.R. Allen Road north of Sheppard Avenue West will be reduced to one lane beginning at 8:00 p.m. on Friday until 6:00 a.m. on Monday.
-
CANCELLED: Overnight Work at York University, Concrete Pour Scheduled for Tuesday, July 22, 2014
July 17, 2014Overnight construction will take place beginning Tuesday, July 22, 2014 at 2:30 a.m. to 3:00 p.m.
-
Overnight Work at York University, Concrete Pours Scheduled for Thursday, July 17, 2014
July 14, 2014Overnight construction will take place beginning Thursday, July 17, 2014 at 2:30 a.m. to 3:00 p.m.
-
RESCHEDULED: Overnight Work at York University, First Major Concrete Pour Rescheduled to Wednesday, July 9, 2014
July 7, 2014The first major concrete pour is scheduled for Wednesday, July 9, 2014. Overnight construction will take place beginning at 2:30 a.m. to 3 p.m.
-
Overnight Work at York University, First Major Concrete Pour on Monday, July 7, 2014
July 3, 2014The first major concrete pour is scheduled for Monday, July 7, 2014. Overnight construction will take place beginning at 2:30 a.m. to 3 p.m.
-
Lane Restriction on Transit Only Traffic Bridge at York University, July 5 and 6, 2014
July 3, 2014On Saturday and Sunday the York Boulevard transit bridge into the Harry W. Arthurs Common at York University will have lane restrictions.