Finch West Station Construction Newsletter - Summer 2013

September 3, 2013

Photo of Finch West Station Entrance

What is happening at Keele and Finch?

TTC is building the Toronto-York Spadina Subway Extension, a six station 8.6 kilometre line that will extend from the existing Downsview Station and will end at Highway 7, west of Jane Street. The second station on the subway extension will be Finch West Station, to be located under Keele Street, north of Finch Avenue West.

A major section of tunnels was completed on March 5, 2013, linking Finch West Station to Downsview Station. A special three tunnel structure, under Keele Street at the Hydro corridor, is being constructed using Sequential Excavation Method (SEM) tunnelling.

Finch West Station construction is progressing well. The station walls are being built and the contractor has begun pouring concrete for the concourse level. During some concrete pours, southbound Keele Street will be closed from Murray Ross Parkway to Toro Road.

Photo of construction at Keele St. and Finch Ave.

Construction Work Hours

The City of Toronto has approved a noise by-law amendment for major transit projects which allows contractors to work extended hours and on weekends for the duration of the project, when required. Extended work hours are expected to be in effect in the Keele/Finch area this spring and summer.

Finch West Station construction work is permitted under the noise by-law from 7:00 a.m. to 11:00 p.m., seven days per week. The contractor has applied for an exemption to the noise by-law for major concrete pours this spring and summer for work outside of these hours. Construction Notices will be sent out before extended work hours begin to keep residents and businesses informed.

Keele-Finch detour in effect. Watch for future notices of changes to traffic detours.

Map of Southbound Keele Closure

TTC Bus Route Services

Transit delays can be expected during peak times on buses:

Bus stops may be temporarily relocated for construction. Watch for posted notices.

What we are doing to keep you moving during construction:

 Photo of Finch West Station Box
Finch West Station box looking south. (May 2013)

Photo of double breakthrough of tunnel boring machines
Double breakthrough of tunnel boring machines Yorkie and Torkie at the Keele Street extraction shaft located north of Finch. (Nov 29, 2012)

Photo of disassembly of tunnel boring machine
Disassembling Moley (tunnel boring machine) at the extraction shaft located south of Finch. (Jan 23, 2013)

Construction of Finch West Subway Station

A section of the construction site north of Toro Road on Keele Street is being backfilled this spring and the area will be used for the installation of track and other tunnel equipment. The drop shafts in the photo shown below are large concrete boxes used by construction crews to lower and deliver subway equipment and materials down into the tunnels. The area where the drop shafts are located was used as an extraction shaft during tunnelling to remove the tunnel boring machines “Holey” and “Moley”.

Aerial photo of Keele St. and Finch Ave. W. construction
This aerial photo of Keele Street and Finch Avenue West was taken on April 29, 2013.

The Toronto-York Spadina Subway Extension project is jointly funded by the Government of Canada, the Province of Ontario, the City of Toronto and The Regional Municipality of York.

For More Information:

1120 Finch Avenue West, Suite 800, 8th Floor North York, ON
Hours: Monday & Fridays: 10:00 a.m - 4:00 p.m. and Thursday: 2:00 p.m - 5:00 p.m.

Pour de plus amples renseignements sur le service
de la TTC, appelez le 1.800.223.6192

Per maggiori informazioni sui servizi TTC chiamate
il 1.800.223.6192

Para mayor información sobre los servicios de la
TTC, llame al 1.800.223.6192

Para sa karag dagang impor mas yon tungkol sa
TTC, tumawag sa 1.800.223.6192

Para mais informações relacionadas com os
transportes públicos (TTC), contacte-nos através
do 1.800.223.6192.

Please support the Keele and Finch local neighbourhood shops and businesses during subway construction.

Bus Route Changes

TTC Bus

Review the new changes to bus routes in the area to connect to the new subway extension.

Read about it here!

Need Information

To contact us for information about the project:

Call 416-393-4636 (INFO) automated information available 24 hours daily.

Contact the Project

Photo Gallery

Check out the latest construction photos and project YouTube videos.

Click here to view the Photo Gallery.

Project News