TTC Easier Access Project - Station Completion Schedule
Schedule for all stations to be completed.
Stations | Complete in |
---|---|
College | 2025 |
Lawrence | 2025 |
Greenwood | 2025 |
Christie | 2025 |
Summerhill | 2025 |
High Park | 2025 |
Museum | 2025 |
Rosedale | 2025 |
Warden |
2025 |
Spadina |
2026 |
King | 2026 |
Islington | 2026 |
Old Mill | TBD* |
*Subject to completion of the expropriation process for the required property.