Construction at Castle Frank Station began in late Fall 2021 and is scheduled to be completed in 2024.

castle-frank-section

Cross section image of station elevators

This work will include:

  • Two new elevators, one to each passenger platform
  • Improved signage
  • CCTV - security cameras along the accessible pathway
  • Accessible sliding doors at the main entrance
 Work hours

Work is generally taking place Monday to Friday between 7 a.m. and 7 p.m. Some work on weekends between 9 a.m. and 5 p.m. may be required to expedite the project.

TTC service

Access to the station, bus and subway service will be maintained throughout construction.

  

For further information:

Paul Tran
Community Liaison
647-461-5133
paul.tran@ttc.ca